Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 14
- Date
- 2025-08-31
- Hijri
- 8 Rabiʻ I 1447 AH
- Reference
- PAY-2024-006-14
Interim payment certificate no. (14)
For the work of August 2025
- Contract number
- RC/2024/006
- Supplier-portal reference
- 2401430082
- Contract
- Training & Employment Centre complex — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Training & Employment Centre Complex
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 28,000,000
- Current contract value
- 29,200,000including variations of SAR 1.2M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 11,597,500 |
| 2 | Less: previous certificates | (10,670,000) |
| 3 | Value of work in this certificate | 927,500 |
| 4 | Less: retention (10%) | (92,750) |
| 5 | Less: advance payment recovery (10%) | (92,750) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (185,500) |
| 8 | Net before VAT | 742,000 |
| 9 | Add: value added tax (15%) | 111,300 |
| 10 | Net amount payable to the contractor | 853,300 |
Amount in words: Eight hundred fifty-three thousand three hundred Saudi riyals only
Retention held up to this certificate: SAR 1.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,044,000 | 1,742,750 | 130,200 | 1,872,950 | 92% |
| Earthworks & foundations | 5,256,000 | 2,711,300 | 211,250 | 2,922,550 | 56% |
| Concrete & structural works | 9,052,000 | 3,636,300 | 318,450 | 3,954,750 | 44% |
| Mechanical, electrical & plumbing | 7,008,000 | 1,770,050 | 178,350 | 1,948,400 | 28% |
| Finishes & external works | 4,380,000 | 705,800 | 77,050 | 782,850 | 18% |
| Testing & commissioning | 1,460,000 | 103,800 | 12,200 | 116,000 | 8% |
| Total | 29,200,000 | 10,670,000 | 927,500 | 11,597,500 | 40% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani