Certificate ⁦20⁩ — March 2026

Training & Employment Centre complex — civil & MEP works

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
20
Date
⁦2026-04-19⁩
Hijri
2 Dhuʻl-Qiʻdah 1447 AH
Reference
PAY-2024-006-20

Interim payment certificate no. (⁦20⁩)

For the work of March 2026

Contract number
RC/2024/006
Supplier-portal reference
2401430082
Contract
Training & Employment Centre complex — civil & MEP works
Contractor
Al-Ufuq General Contracting Co.
Contractor VAT number
320500924170003
Project
Training & Employment Centre Complex
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
28,000,000
Current contract value
29,200,000including variations of SAR 1.2M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date16,689,500
2Less: previous certificates(16,062,000)
3Value of work in this certificate627,500
4Less: retention (⁦10%⁩)(62,750)
5Less: advance payment recovery (⁦10%⁩)(62,750)
6Less: delay and breach penalties0
7Total deductions(125,500)
8Net before VAT502,000
9Add: value added tax (15%)75,300
10Net amount payable to the contractor577,300

Amount in words: Five hundred seventy-seven thousand three hundred Saudi riyals only

Retention held up to this certificate: SAR 1.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation2,044,0001,984,65059,3502,044,000⁦100%⁩
Earthworks & foundations5,256,0004,705,250151,8504,857,100⁦92%⁩
Concrete & structural works9,052,0005,475,050216,0505,691,100⁦63%⁩
Mechanical, electrical & plumbing7,008,0002,672,350131,5002,803,850⁦40%⁩
Finishes & external works4,380,0001,067,45059,1001,126,550⁦26%⁩
Testing & commissioning1,460,000157,2509,650166,900⁦11%⁩
Total29,200,00016,062,000627,50016,689,500⁦57%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Khalil I. Al-Dosari

Al-Dosari⁦2026-04-19⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-04-21⁩

Project manager

Eng. Shahad M. Al-Malki

Al-Malki⁦2026-04-24⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-04-27⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-04-30⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-19⁩

    Eng. Khalil I. Al-Dosari

  2. Engineer verifies quantities⁦2026-04-21⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-24⁩

    Eng. Shahad M. Al-Malki · Senior Project Manager — Buildings & Facilities

    Took 3 days

  4. Payment order prepared⁦2026-04-27⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-30⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Shahad M. Al-Malki → Dr. Abdullah S. Al-Qahtani

Certificate history

30 April 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-04-30 13:00

27 April 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-04-27 13:00

24 April 2026

  1. Approval: Eng. Shahad M. Al-Malki signed “Project manager certifies”

    2026-04-24 13:00

21 April 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-04-21 13:00

19 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-19 09:00