Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 19
- Date
- 2026-03-11
- Hijri
- 22 Ramadan 1447 AH
- Reference
- PAY-2024-006-19
Interim payment certificate no. (19)
For the work of February 2026
- Contract number
- RC/2024/006
- Supplier-portal reference
- 2401430082
- Contract
- Training & Employment Centre complex — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Training & Employment Centre Complex
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 28,000,000
- Current contract value
- 29,200,000including variations of SAR 1.2M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 16,062,000 |
| 2 | Less: previous certificates | (15,363,000) |
| 3 | Value of work in this certificate | 699,000 |
| 4 | Less: retention (10%) | (69,900) |
| 5 | Less: advance payment recovery (10%) | (69,900) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (139,800) |
| 8 | Net before VAT | 559,200 |
| 9 | Add: value added tax (15%) | 83,880 |
| 10 | Net amount payable to the contractor | 643,080 |
Amount in words: Six hundred forty-three thousand eighty Saudi riyals only
Retention held up to this certificate: SAR 1.6M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,044,000 | 1,974,050 | 69,950 | 2,044,000 | 100% |
| Earthworks & foundations | 5,256,000 | 4,429,200 | 168,450 | 4,597,650 | 87% |
| Concrete & structural works | 9,052,000 | 5,236,550 | 240,600 | 5,477,150 | 61% |
| Mechanical, electrical & plumbing | 7,008,000 | 2,553,650 | 144,750 | 2,698,400 | 39% |
| Finishes & external works | 4,380,000 | 1,019,450 | 64,750 | 1,084,200 | 25% |
| Testing & commissioning | 1,460,000 | 150,100 | 10,500 | 160,600 | 11% |
| Total | 29,200,000 | 15,363,000 | 699,000 | 16,062,000 | 55% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani