AI insight
An escalated contract needs a decision
Open claims: 2; pending variations worth SAR 930K. A settlement session with the contractor is advised before deciding the next certificate.
Confidence84%
RC/2024/006
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 930K — if approved the value becomes SAR 30.1M
64% of the current value paid
Paid
18.6Mof a current value of SAR 29.2M
AI insight
Open claims: 2; pending variations worth SAR 930K. A settlement session with the contractor is advised before deciding the next certificate.
Value of each certificate
The last 14 — gross and net
Approved: 24
Count: 25 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 25September 2026 | 2026-10-13 | 490K | 49K | 111.5K | 49.4K | 378.9K | Escalated | |
| Certificate 24August 2026 | 2026-09-13 | 555K | 55.5K | 55.5K | 66.6K | 510.6K | Approved | |
| Certificate 23July 2026 | 2026-08-12 | 334K | 33.4K | 33.4K | 40.1K | 307.3K | Approved | |
| Certificate 22June 2026 | 2026-07-05 | 417K | 41.7K | 41.7K | 50K | 383.6K | Approved | |
| Certificate 21May 2026 | 2026-05-27 | 579.5K | 58K | 58K | 69.5K | 533.1K | Approved | |
| Certificate 20March 2026 | 2026-04-19 | 627.5K | 62.8K | 62.8K | 75.3K | 577.3K | Approved | |
| Certificate 19February 2026 | 2026-03-11 | 699K | 69.9K | 69.9K | 83.9K | 643.1K | Approved | |
| Certificate 18January 2026 | 2026-02-01 | 899.5K | 90K | 90K | 107.9K | 827.5K | Approved | |
| Certificate 17December 2025 | 2025-12-24 | 821K | 82.1K | 82.1K | 98.5K | 755.3K | Approved | |
| Certificate 16October 2025 | 2025-11-16 | 962K | 96.2K | 96.2K | 115.4K | 885K | Approved | |
| Certificate 15September 2025 | 2025-10-08 | 1.1M | 108.3K | 108.3K | 130K | 996.4K | Approved | |
| Certificate 14August 2025 | 2025-08-31 | 927.5K | 92.8K | 92.8K | 111.3K | 853.3K | Approved | |
| Certificate 13July 2025 | 2025-07-23 | 1.1M | 113.8K | 113.8K | 136.6K | 1M | Approved | |
| Certificate 12May 2025 | 2025-06-15 | 1.1M | 109.2K | 109.2K | 131K | 1M | Approved | |
| Certificate 11April 2025 | 2025-05-07 | 964.5K | 96.5K | 96.5K | 115.7K | 887.3K | Approved | |
| Certificate 10March 2025 | 2025-03-30 | 1.2M | 115.3K | 115.3K | 138.3K | 1.1M | Approved | |
| Certificate 9January 2025 | 2025-02-19 | 958.5K | 95.9K | 95.9K | 115K | 881.8K | Approved | |
| Certificate 8December 2024 | 2025-01-12 | 917K | 91.7K | 91.7K | 110K | 843.6K | Approved | |
| Certificate 7November 2024 | 2024-12-04 | 980.5K | 98.1K | 98.1K | 117.7K | 902.1K | Approved | |
| Certificate 6October 2024 | 2024-10-27 | 748.5K | 74.9K | 74.9K | 89.8K | 688.6K | Approved | |
| Certificate 5August 2024 | 2024-09-18 | 751K | 75.1K | 75.1K | 90.1K | 690.9K | Approved | |
| Certificate 4July 2024 | 2024-08-11 | 674.5K | 67.5K | 67.5K | 80.9K | 620.5K | Approved | |
| Certificate 3June 2024 | 2024-07-03 | 504K | 50.4K | 50.4K | 60.5K | 463.7K | Approved | |
| Certificate 2May 2024 | 2024-05-26 | 457.5K | 45.8K | 45.8K | 54.9K | 420.9K | Approved | |
| Certificate 1March 2024 | 2024-04-17 | 332K | 33.2K | 33.2K | 39.8K | 305.4K | Approved |