Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 7
- Date
- 2024-12-04
- Hijri
- 3 Jumada II 1446 AH
- Reference
- PAY-2024-006-07
Interim payment certificate no. (7)
For the work of November 2024
- Contract number
- RC/2024/006
- Supplier-portal reference
- 2401430082
- Contract
- Training & Employment Centre complex — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Training & Employment Centre Complex
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 28,000,000
- Current contract value
- 29,200,000including variations of SAR 1.2M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,448,000 |
| 2 | Less: previous certificates | (3,467,500) |
| 3 | Value of work in this certificate | 980,500 |
| 4 | Less: retention (10%) | (98,050) |
| 5 | Less: advance payment recovery (10%) | (98,050) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (196,100) |
| 8 | Net before VAT | 784,400 |
| 9 | Add: value added tax (15%) | 117,660 |
| 10 | Net amount payable to the contractor | 902,060 |
Amount in words: Nine hundred two thousand sixty Saudi riyals only
Retention held up to this certificate: SAR 444.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,044,000 | 566,400 | 151,950 | 718,350 | 35% |
| Earthworks & foundations | 5,256,000 | 881,200 | 239,700 | 1,120,900 | 21% |
| Concrete & structural works | 9,052,000 | 1,181,700 | 335,050 | 1,516,750 | 17% |
| Mechanical, electrical & plumbing | 7,008,000 | 575,150 | 172,100 | 747,250 | 11% |
| Finishes & external works | 4,380,000 | 229,350 | 70,900 | 300,250 | 7% |
| Testing & commissioning | 1,460,000 | 33,700 | 10,800 | 44,500 | 3% |
| Total | 29,200,000 | 3,467,500 | 980,500 | 4,448,000 | 15% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani