Training & Employment Centre Complex
Remove from watchlistA 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.
Budget (BAC)
Actual cost
70% of budget
Progress
Estimate at completion
SAR +7M
SPI · CPI
Forecast finish
152 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure7 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-09-10 | 2025-01-10 | +122 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-02-25 | 2025-09-29 | +216 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-11-05 | 2026-10-26 | +355 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-16 | 2027-04-15 | +273 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-06-02 | +153 days | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
57%Awaiting acceptance
10%Not handed in
33%Deliverable flow
Display options
| Project plan & baseline007-D1 | 3% | CRT-007-01 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2024-06-18 | V1 | 3 of 3 |
| Monitoring & reporting007-D2 | 3% | CRT-007-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2024-09-10 | V1 | 3 of 3 |
| Detailed design007-D3 | 6% | CRT-007-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2024-12-03 | V1 | 3 of 3 |
| Permits & approvals007-D4 | 6% | CRT-007-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-02-25 | V1 | 3 of 3 |
| Site works & excavation007-D5 | 13% | CRT-007-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-05-21 | V1 | 3 of 3 |
| Structure007-D6 | 13% | CRT-007-06 | Approved | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-08-13 | V1 | 3 of 3 |
| Finishes007-D7 | 13% | CRT-007-07 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-11-05 | V1 | 3 of 3 |
| Supply007-D8 | 10% | — | Submitted | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-01-28 | V1 | 1 of 3 |
| Installation007-D9 | 10% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-04-22 | V0 | 0 of 3 |
| Testing & commissioning007-D10 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-07-16 | V0 | 0 of 3 |
| Provisional acceptance007-D11 | 7% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-08 | V0 | 0 of 3 |
| Final acceptance007-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-12-31 | V0 | 0 of 3 |
| Total · 12 | 100% |