Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 6
- Date
- 2024-10-27
- Hijri
- 24 Rabiʻ II 1446 AH
- Reference
- PAY-2024-006-06
Interim payment certificate no. (6)
For the work of October 2024
- Contract number
- RC/2024/006
- Supplier-portal reference
- 2401430082
- Contract
- Training & Employment Centre complex — civil & MEP works
- Contractor
- Al-Ufuq General Contracting Co.
- Contractor VAT number
- 320500924170003
- Project
- Training & Employment Centre Complex
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- 28,000,000
- Current contract value
- 29,200,000including variations of SAR 1.2M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 3,467,500 |
| 2 | Less: previous certificates | (2,719,000) |
| 3 | Value of work in this certificate | 748,500 |
| 4 | Less: retention (10%) | (74,850) |
| 5 | Less: advance payment recovery (10%) | (74,850) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (149,700) |
| 8 | Net before VAT | 598,800 |
| 9 | Add: value added tax (15%) | 89,820 |
| 10 | Net amount payable to the contractor | 688,620 |
Amount in words: Six hundred eighty-eight thousand six hundred twenty Saudi riyals only
Retention held up to this certificate: SAR 346.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 2,044,000 | 442,850 | 117,150 | 560,000 | 27% |
| Earthworks & foundations | 5,256,000 | 689,450 | 184,350 | 873,800 | 17% |
| Concrete & structural works | 9,052,000 | 926,750 | 255,650 | 1,182,400 | 13% |
| Mechanical, electrical & plumbing | 7,008,000 | 452,500 | 130,050 | 582,550 | 8% |
| Finishes & external works | 4,380,000 | 180,800 | 53,250 | 234,050 | 5% |
| Testing & commissioning | 1,460,000 | 26,650 | 8,050 | 34,700 | 2% |
| Total | 29,200,000 | 2,719,000 | 748,500 | 3,467,500 | 12% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Khalil I. Al-Dosari
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Shahad M. Al-Malki
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani