Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 16
- Date
- 2026-09-14
- Hijri
- 3 Rabiʻ II 1448 AH
- Reference
- PAY-2026-010
Interim payment certificate no. (16)
For the work of August 2026
- Contract number
- RC/2024/019
- Supplier-portal reference
- 2402340251
- Contract
- Second Industrial City branch — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 11,400,000
- Current contract value
- 11,880,000including variations of SAR 480K
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,920,000 |
| 2 | Less: previous certificates | (4,605,000) |
| 3 | Value of work in this certificate | 315,000 |
| 4 | Less: retention (10%) | (31,500) |
| 5 | Less: advance payment recovery (10%) | (31,500) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (63,000) |
| 8 | Net before VAT | 252,000 |
| 9 | Add: value added tax (15%) | 37,800 |
| 10 | Net amount payable to the contractor | 289,800 |
Amount in words: Two hundred eighty-nine thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 492K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 831,600 | 750,750 | 43,850 | 794,600 | 96% |
| Earthworks & foundations | 2,138,400 | 1,168,550 | 71,300 | 1,239,850 | 58% |
| Concrete & structural works | 3,682,800 | 1,569,500 | 108,200 | 1,677,700 | 46% |
| Mechanical, electrical & plumbing | 2,851,200 | 765,550 | 61,000 | 826,550 | 29% |
| Finishes & external works | 1,782,000 | 305,650 | 26,450 | 332,100 | 19% |
| Testing & commissioning | 594,000 | 45,000 | 4,200 | 49,200 | 8% |
| Total | 11,880,000 | 4,605,000 | 315,000 | 4,920,000 | 41% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani