RC/2024/019
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 1.1M — if approved the value becomes SAR 13M
41% of the current value paid
Paid
4.9Mof a current value of SAR 11.9M
Value of each certificate
The last 14 — gross and net
Approved: 16
Count: 17 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 17September 2026 | 2026-10-14 | 295K | 29.5K | 29.5K | 35.4K | 271.4K | Submitted | |
| Certificate 16August 2026 | 2026-09-14 | 315K | 31.5K | 31.5K | 37.8K | 289.8K | Approved | |
| Certificate 15July 2026 | 2026-08-13 | 144K | 14.4K | 14.4K | 17.3K | 132.5K | Approved | |
| Certificate 14June 2026 | 2026-06-29 | 190.5K | 19.1K | 19.1K | 22.9K | 175.3K | Approved | |
| Certificate 13April 2026 | 2026-05-14 | 278.5K | 27.9K | 27.9K | 33.4K | 256.2K | Approved | |
| Certificate 12March 2026 | 2026-03-30 | 322K | 32.2K | 32.2K | 38.6K | 296.2K | Approved | |
| Certificate 11January 2026 | 2026-02-12 | 328.5K | 32.9K | 32.9K | 39.4K | 302.2K | Approved | |
| Certificate 10December 2025 | 2025-12-29 | 433.5K | 43.4K | 43.4K | 52K | 398.8K | Approved | |
| Certificate 9October 2025 | 2025-11-13 | 393K | 39.3K | 39.3K | 47.2K | 361.6K | Approved | |
| Certificate 8September 2025 | 2025-09-29 | 402K | 40.2K | 40.2K | 48.2K | 369.8K | Approved | |
| Certificate 7July 2025 | 2025-08-15 | 456K | 45.6K | 45.6K | 54.7K | 419.5K | Approved | |
| Certificate 6June 2025 | 2025-06-30 | 355.5K | 35.6K | 35.6K | 42.7K | 327.1K | Approved | |
| Certificate 5April 2025 | 2025-05-16 | 368.5K | 36.9K | 36.9K | 44.2K | 339K | Approved | |
| Certificate 4March 2025 | 2025-03-31 | 335K | 33.5K | 33.5K | 40.2K | 308.2K | Approved | |
| Certificate 3January 2025 | 2025-02-14 | 241K | 24.1K | 24.1K | 28.9K | 221.7K | Approved | |
| Certificate 2December 2024 | 2024-12-30 | 215.5K | 21.6K | 21.6K | 25.9K | 198.3K | Approved | |
| Certificate 1October 2024 | 2024-11-15 | 141.5K | 14.2K | 14.2K | 17K | 130.2K | Approved |