Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 8
- Date
- 2025-09-29
- Hijri
- 7 Rabiʻ II 1447 AH
- Reference
- PAY-2024-019-08
Interim payment certificate no. (8)
For the work of September 2025
- Contract number
- RC/2024/019
- Supplier-portal reference
- 2402340251
- Contract
- Second Industrial City branch — civil & ground-improvement works
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
- Contract period
- 2024-10-01 — 2027-03-31
- Original contract value
- 11,400,000
- Current contract value
- 11,880,000including variations of SAR 480K
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,515,000 |
| 2 | Less: previous certificates | (2,113,000) |
| 3 | Value of work in this certificate | 402,000 |
| 4 | Less: retention (10%) | (40,200) |
| 5 | Less: advance payment recovery (10%) | (40,200) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (80,400) |
| 8 | Net before VAT | 321,600 |
| 9 | Add: value added tax (15%) | 48,240 |
| 10 | Net amount payable to the contractor | 369,840 |
Amount in words: Three hundred sixty-nine thousand eight hundred forty Saudi riyals only
Retention held up to this certificate: SAR 251.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 831,600 | 345,100 | 61,100 | 406,200 | 49% |
| Earthworks & foundations | 2,138,400 | 536,900 | 96,900 | 633,800 | 30% |
| Concrete & structural works | 3,682,800 | 720,100 | 137,500 | 857,600 | 23% |
| Mechanical, electrical & plumbing | 2,851,200 | 350,550 | 71,950 | 422,500 | 15% |
| Finishes & external works | 1,782,000 | 139,800 | 29,950 | 169,750 | 10% |
| Testing & commissioning | 594,000 | 20,550 | 4,600 | 25,150 | 4% |
| Total | 11,880,000 | 2,113,000 | 402,000 | 2,515,000 | 21% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani