Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦14⁩ — July 2026

Supply & install smart access, visitor & event management and the monitoring room

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
14
Date
⁦2026-08-09⁩
Hijri
26 Safar 1448 AH
Reference
PAY-2026-003

Interim payment certificate no. (⁦14⁩)

For the work of July 2026

Contract number
RC/2025/002
Supplier-portal reference
2503250420
Contract
Supply & install smart access, visitor & event management and the monitoring room
Contractor
Smart Link Telecom & Security Systems Co.
Contractor VAT number
340303165720003
Project
Smart Access, Visitor & Event Management at HQ & the Branches
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
3,075,000
Current contract value
3,075,000
Linked milestone
Testing & commissioning · MS-G5 Final handover

Certificate summary (SAR)

1Total value of work completed to date2,510,000
2Less: previous certificates(2,345,000)
3Value of work in this certificate165,000
4Less: retention (⁦10%⁩)(16,500)
5Less: advance payment recovery (⁦10%⁩)(16,500)
6Less: delay and breach penalties0
7Total deductions(33,000)
8Net before VAT132,000
9Add: value added tax (15%)19,800
10Net amount payable to the contractor151,800

Amount in words: One hundred fifty-one thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 251K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation215,250208,0507,200215,250⁦100%⁩
Earthworks & foundations553,500531,05022,450553,500⁦100%⁩
Concrete & structural works953,250893,85059,400953,250⁦100%⁩
Mechanical, electrical & plumbing738,000539,25054,200593,450⁦80%⁩
Finishes & external works461,250150,90018,550169,450⁦37%⁩
Testing & commissioning153,75021,9003,20025,100⁦16%⁩
Total3,075,0002,345,000165,0002,510,000⁦82%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Ammar Y. Bakhashab

Bakhashab⁦2026-08-09⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-08-11⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2026-08-14⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-08-17⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-08-20⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-09⁩

    Eng. Ammar Y. Bakhashab

  2. Engineer verifies quantities⁦2026-08-11⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-08-14⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2026-08-17⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-08-20⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneTesting & commissioningLate · ⁦2026-09-12⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

20 August 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-08-20 13:00

17 August 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-08-17 13:00

14 August 2026

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2026-08-14 13:00

11 August 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-08-11 13:00

9 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-09 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close