RC/2025/002
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
2.5Mof a current value of SAR 3.1M
Value of each certificate
The last 14 — gross and net
Approved: 14
Count: 14 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 14July 2026 | 2026-08-09 | 165K | 16.5K | 16.5K | 19.8K | 151.8K | Approved | |
| Certificate 13June 2026 | 2026-07-08 | 87K | 8,700 | 8,700 | 10.4K | 80K | Approved | |
| Certificate 12May 2026 | 2026-06-01 | 130K | 13K | 13K | 15.6K | 119.6K | Approved | |
| Certificate 11April 2026 | 2026-04-24 | 154.5K | 15.5K | 15.5K | 18.5K | 142.1K | Approved | |
| Certificate 10February 2026 | 2026-03-18 | 220K | 22K | 22K | 26.4K | 202.4K | Approved | |
| Certificate 9January 2026 | 2026-02-09 | 215K | 21.5K | 21.5K | 25.8K | 197.8K | Approved | |
| Certificate 8December 2025 | 2026-01-02 | 231K | 23.1K | 23.1K | 27.7K | 212.5K | Approved | |
| Certificate 7November 2025 | 2025-11-26 | 272K | 27.2K | 27.2K | 32.6K | 250.2K | Approved | |
| Certificate 6September 2025 | 2025-10-20 | 218K | 21.8K | 21.8K | 26.2K | 200.6K | Approved | |
| Certificate 5August 2025 | 2025-09-12 | 231K | 23.1K | 23.1K | 27.7K | 212.5K | Approved | |
| Certificate 4July 2025 | 2025-08-06 | 212.5K | 21.3K | 21.3K | 25.5K | 195.5K | Approved | |
| Certificate 3June 2025 | 2025-06-30 | 152K | 15.2K | 15.2K | 18.2K | 139.8K | Approved | |
| Certificate 2May 2025 | 2025-05-23 | 136K | 13.6K | 13.6K | 16.3K | 125.1K | Approved | |
| Certificate 1March 2025 | 2025-04-16 | 86K | 8,600 | 8,600 | 10.3K | 79.1K | Approved |