Certificate ⁦3⁩ — June 2025

Supply & install smart access, visitor & event management and the monitoring room

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2025-06-30⁩
Hijri
5 Muharram 1447 AH
Reference
PAY-2025-002-03

Interim payment certificate no. (⁦3⁩)

For the work of June 2025

Contract number
RC/2025/002
Supplier-portal reference
2503250420
Contract
Supply & install smart access, visitor & event management and the monitoring room
Contractor
Smart Link Telecom & Security Systems Co.
Contractor VAT number
340303165720003
Project
Smart Access, Visitor & Event Management at HQ & the Branches
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
3,075,000
Current contract value
3,075,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date374,000
2Less: previous certificates(222,000)
3Value of work in this certificate152,000
4Less: retention (⁦10%⁩)(15,200)
5Less: advance payment recovery (⁦10%⁩)(15,200)
6Less: delay and breach penalties0
7Total deductions(30,400)
8Net before VAT121,600
9Add: value added tax (15%)18,240
10Net amount payable to the contractor139,840

Amount in words: One hundred thirty-nine thousand eight hundred forty Saudi riyals only

Retention held up to this certificate: SAR 37.4K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation215,25036,60023,75060,350⁦28%⁩
Earthworks & foundations553,50056,85037,40094,250⁦17%⁩
Concrete & structural works953,25075,65051,900127,550⁦13%⁩
Mechanical, electrical & plumbing738,00036,40026,45062,850⁦9%⁩
Finishes & external works461,25014,40010,85025,250⁦5%⁩
Testing & commissioning153,7502,1001,6503,750⁦2%⁩
Total3,075,000222,000152,000374,000⁦12%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Ammar Y. Bakhashab

Bakhashab⁦2025-06-30⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-07-02⁩

Project manager

Eng. Waleed O. Al-Juhani

Al-Juhani⁦2025-07-05⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-07-08⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-07-11⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-06-30⁩

    Eng. Ammar Y. Bakhashab

  2. Engineer verifies quantities⁦2025-07-02⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-07-05⁩

    Eng. Waleed O. Al-Juhani · Director, Facilities Operations & Maintenance

    Took 3 days

  4. Payment order prepared⁦2025-07-08⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-07-11⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-08-19⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-12-10⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Waleed O. Al-Juhani → Dr. Abdullah S. Al-Qahtani

Certificate history

11 July 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-07-11 13:00

8 July 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-07-08 13:00

5 July 2025

  1. Approval: Eng. Waleed O. Al-Juhani signed “Project manager certifies”

    2025-07-05 13:00

2 July 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-07-02 13:00

30 June 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-06-30 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close