Smart Access, Visitor & Event Management at HQ & the Branches
Add to watchlist1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
SAR +236K
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-24 | 2025-08-03 | +40 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-01 | 2025-12-10 | +70 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-26 | 2026-06-21 | +115 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-24 | 2026-12-22 | +151 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-10-31 | 2027-01-11 | +72 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
79%Awaiting acceptance
9%Not handed in
12%Deliverable flow
Display options
| Project plan & baseline013-D1 | 3% | CRT-013-01 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-05-06 | V1 | 3 of 3 |
| Monitoring & reporting013-D2 | 3% | CRT-013-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-06-24 | V1 | 3 of 3 |
| Detailed design013-D3 | 6% | CRT-013-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-08-13 | V1 | 3 of 3 |
| Permits & approvals013-D4 | 6% | CRT-013-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-10-01 | V1 | 3 of 3 |
| Site works & excavation013-D5 | 13% | CRT-013-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-11-19 | V1 | 3 of 3 |
| Structure013-D6 | 13% | CRT-013-06 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-01-08 | V1 | 3 of 3 |
| Finishes013-D7 | 13% | CRT-013-07 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-02-26 | V1 | 3 of 3 |
| Supply013-D8 | 11% | CRT-013-08 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-04-17 | V1 | 3 of 3 |
| Installation013-D9 | 11% | CRT-013-09 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-06-05 | V1 | 3 of 3 |
| Testing & commissioning013-D10 | 9% | — | Submitted | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-07-24 | V1 | 1 of 3 |
| Provisional acceptance013-D11 | 6% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-09-12 | V0 | 0 of 3 |
| Final acceptance013-D12 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-10-31 | V0 | 0 of 3 |
| Total · 12 | 100% |