Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-013At risk4ExecutionConstructionIn progress

Smart Access, Visitor & Event Management at HQ & the Branches

Add to watchlist

1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 3.7M

Actual cost

SAR 3.1M

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 3.9M

SAR +236K

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • No documents

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents0
Linked to tasks0
Tasks with documents0

This project has no documents yet — upload the first one to link it to its stage and tasks.

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 013-D1Project plan & baselinePRJ-2026-013_1.1_v1.pdfApprovedDeliverable
  • 013-D2Monitoring & reportingPRJ-2026-013_1.2_v1.pdfApprovedDeliverable
  • 013-D3Detailed designPRJ-2026-013_2.1_v1.pdfApprovedDeliverable
  • 013-D4Permits & approvalsPRJ-2026-013_2.2_v1.pdfApprovedDeliverable
  • 013-D5Site works & excavationPRJ-2026-013_3.1_v1.pdfApprovedDeliverable
  • 013-D6StructurePRJ-2026-013_3.2_v1.pdfApprovedDeliverable
  • 013-D7FinishesPRJ-2026-013_3.3_v1.pdfApprovedDeliverable
  • 013-D8SupplyPRJ-2026-013_4.1_v1.pdfApprovedDeliverable
  • 013-D9InstallationPRJ-2026-013_4.2_v1.pdfApprovedDeliverable
  • 013-D10Testing & commissioningPRJ-2026-013_4.3_v1.pdfIn reviewDeliverable
  • 013-D11Provisional acceptanceNo evidence filed yetDraftDeliverable
  • 013-D12Final acceptanceNo evidence filed yetDraftDeliverable
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close