Smart Access, Visitor & Event Management at HQ & the Branches
Add to watchlist1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
SAR +236K
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started