PRJ-2026-013At risk4ExecutionConstructionIn progress
Smart Access, Visitor & Event Management at HQ & the Branches
Add to watchlist1,200 cameras and gates and QR check-in for events at headquarters and the branches, with a central monitoring room, starting with the conference hall at the current headquarters.
Project managerEng. Waleed O. Al-JuhaniProject sponsorSarah A. Al-QarniProgrammeSmart Headquarters & Communication Channels Programme
Early warning: 58% chance of slipping within 45 days
Budget (BAC)
SAR 3.7M
Actual cost
SAR 3.1M
84% of budget
Progress
79%Awaiting acceptance 9%
Estimate at completion
SAR 3.9M
SAR +236K
SPI · CPI
0.88Schedule performance index · 0.880.94Cost performance index · 0.94
Forecast finish
2026-12-15
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started