Riyadh ChamberMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Data-migration quality sets the go-live date

LL-2026-001 · Data · High impact · Published

  1. 1Context⁦The chamber ERP on Dynamics 365 replaces four legacy systems⁩.
  2. 2What happened⁦The second trial migration found 18% of supplier records duplicated or incomplete⁩.
  3. 3ImpactThe Strategy & Projects Steering Committee sent the plan back and a third migration cycle was added.

Recommendation

Estimate data cleansing as its own line in the business case, not inside contingency.

Captured by
Dana S. Al-Saleh
Date
2026-06-3015 Muharram 1448 AH
Applies to
IT · Digital