Planned to date 67%
- SPI
- 0.87
- Forecast finish
- 2027-05-12
- Budget
- SAR 4.3M
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Weekly project team meeting and corrective-plan follow-up.
Held on
26 October 202609:30 – 10:35
60 of 60 min
Wave 1 progress (24 member services)
For informationEng. Sultan F. Al-Ghamdi
20 min
Vendor integration engineer shortfall
DiscussionHussam T. Al-Qurashi
25 min
Nafath test environment readiness
DiscussionHussam T. Al-Qurashi
15 min
Saved as you type
No decisions recorded
Record the decision and put it to a vote if needed.
They show in the task register and on the owner’s calendar
ACT-0301Eng. Sultan F. Al-Ghamdi
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
Planned to date 67%
42 days lateMaterial risks: 2Open impediments: 7Corrective plan CP-2026-01
Change request awaiting decision · CR-2026-004
Add membership transfer & record merge to the first releaseMy Business Portal 2.0 — the Unified Member Journey
Corrective plan awaiting approval · CP-2026-01
My Business Portal 2.0 — the Unified Member JourneyISS-0103 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Three extra vendor integration engineers for four months through change request CR-2026-012
ISS-0101 · My Business Portal 2.0 — the Unified Member Journey
Coordination· Asked from: Dr. Abdullah S. Al-Qahtani
A letter from the Secretary-General to the National Information Center for a dedicated test environment for three months
CP-2026-01 · My Business Portal 2.0 — the Unified Member Journey
PeopleSAR 49K· Asked from: Change Committee
Approve change request CR-2026-012 for three integration engineers
Nothing