Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-032On track5ClosureAgileCompleted

HR Self-Service

Add to watchlist

Completed: 34 HR procedures.

Budget (BAC)

SAR 570K

Actual cost

SAR 538K

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 538K

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2024-05-03⁩
Hijri
24 Shawwal 1445 AH
ApprovedPRJ-2026-032HR Self-Service

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-032
Project
HR Self-Service
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1Objective

Background

Completed: 34 HR procedures.

Project objectives

  1. Innovative, results-driven human capital
  2. Financial sustainability

2Scope

In scope

  • Completed: 34 HR procedures.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2024-05-26⁩
Main deliverable — stage 1⁦2025-01-22⁩
Main deliverable — final stage⁦2025-07-20⁩
Final report⁦2025-09-30⁩
MilestoneDate
Charter approved⁦2024-05-03⁩
Contract signed⁦2024-07-26⁩
50% of works complete⁦2025-01-22⁩
Provisional acceptance⁦2025-08-20⁩
Closure⁦2025-09-30⁩

4RolesAuto-filled

SponsorAuto-filled
Sarah A. Al-Qarni
Project ownerAuto-filled
Abdulmajeed R. Al-Dosari
Project managerAuto-filled
Dana S. Al-Saleh
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 410K
Supervision & consultingSAR 80K
Internal teamSAR 50K
Contingency reserve (5%)SAR 30K
Approved budgetSAR 570K

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2024-04-24⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2024-04-27⁩ 12:30
3Project ownerTechnical acceptanceAbdulmajeed R. Al-DosariProject ownerApproved—⁦2024-04-30⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-05-01⁩ 11:10
5Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2024-05-03⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2024-04-27⁩

Project owner

Abdulmajeed R. Al-Dosari

Approved⁦2024-04-30⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2024-05-01⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2024-05-03⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2024-04-24⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2024-04-27⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Abdulmajeed R. Al-Dosari · Project owner

    Approved · ⁦2024-04-30⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-05-01⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2024-05-03⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-05-03⁩

    Approved version

    • PMO comments addressed

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2024-04-14⁩

    First draft

    • Returned to detail the budget

    Dana S. Al-Saleh