PRJ-2026-032On track5ClosureAgileCompleted

HR Self-Service

Add to watchlist

Completed: 34 HR procedures.

Budget (BAC)

SAR 570K

Actual cost

SAR 538K

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 538K

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 570K split into spent, committed and left, with the estimate at completion

EAC SAR 538K
Revised request SAR 570K
  • Actual spendSAR 538K
  • Committed, not spentSAR 7,000
  • Allotted, uncommittedSAR 7,900
  • Contingency availableSAR 17.1K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 555K
Original budgetwhen the first baseline was approved
SAR 570K
Approved budgetafter approved change requests
SAR 570K
Current budgetavailable to spend now
SAR 570K
Revised budgetif the pending changes are approved
SAR 570K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 545K
Contracts1 active contract
SAR 440K
Purchase orders⁦2⁩ orders
SAR 105K
Remaining budgetapproved less actual
SAR 32K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 538K
Accrualswork done, not yet invoiced
SAR 22K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 538K
ContingencySAR 11.9K drawn of SAR 29K
SAR 17.1K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 555K
ApprovedSAR 570K
Estimate at completionSAR 538K
Approved is SAR 15K (⁦2.7%⁩) above the estimate
The estimate at completion is SAR 17K (⁦3.1%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-02-20⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61032
  • WBS elements⁦5⁩ elements · P-2026-032.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦11⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 11.9K drawn of SAR 29K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 11.9K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.040.040.040.04⁦+0.00⁩
2Analysis & design0.090.090.090.09⁦+0.00⁩
3Build0.220.220.220.21⁦+0.01⁩
4Testing & acceptance0.110.110.110.11⁦+0.00⁩
5Launch & handover0.080.080.080.08⁦+0.00⁩
Unallocated contingency0.020.000.000.01⁦+0.01⁩
Total0.570.550.540.54⁦+0.03⁩

Budget split

WBS

SAR 570K

Budget

  • Management & governanceSAR 44.2K⁦8%⁩
  • Analysis & designSAR 94K⁦16%⁩
  • BuildSAR 221.2K⁦39%⁩
  • Testing & acceptanceSAR 110.6K⁦19%⁩
  • Launch & handoverSAR 82.9K⁦15%⁩
  • Unallocated contingencySAR 17.1K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2025-09-30⁩

SPI(t) ⁦1.00⁩ against the approved finish ⁦2025-09-30⁩

Planned valuePV
SAR 570K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 570K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 538K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 570K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.03⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.06
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 538K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.03⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 538K
  • If the rest goes to planSAR 538K
  • At cost and schedule performanceSAR 538K
  • The PM’s bottom-up estimateSAR 538K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 538K

Variance at completion: ⁦+0.03⁩ SAR M