PRJ-2026-032On track5ClosureAgileCompleted

HR Self-Service

Add to watchlist

Completed: 34 HR procedures.

Budget (BAC)

SAR 570K

Actual cost

SAR 538K

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 538K

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
RC-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
Hijri
17 Jumada I 1448 AH
DraftPRJ-2026-032HR Self-Service

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-032
Project
HR Self-Service
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1PerformanceAuto-filled

Approved budget

SAR 570K

Actual cost

SAR 538K

Cost variance

SAR +32K

Schedule variance

−9 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenAbdulmajeed R. Al-DosariFinal acceptance of every deliverable
Financial settlementOpenKhalid N. Al-MutairiSpend reconciled, commitments closed
Contracts closedOpenKhalid N. Al-MutairiContracts closed, retention released
Documents archivedOpenDana S. Al-SalehDocuments archived with classification
Lessons learnedOpenDana S. Al-SalehLessons-learned session
Benefits handed to their ownerOpenAbdulmajeed R. Al-DosariBenefits handed to their owner with a measurement plan
Final reportOpenDana S. Al-SalehFinal report and its approval
BenefitNew ownerHandover
Staff hours saved by HR automationAbdulmajeed R. Al-DosariPlanned
Paper and printing savingsMunirah A. Al-KhalidiPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableAbdulmajeed R. Al-Dosari⁦2025-09-11⁩
Financial settlement — Spend reconciled, commitments closedKhalid N. Al-Mutairi⁦2025-10-11⁩
Contracts closed — Contracts closed, retention releasedKhalid N. Al-Mutairi⁦2025-10-21⁩
Documents archived — Documents archived with classificationDana S. Al-Saleh⁦2025-10-16⁩
Lessons learned — Lessons-learned sessionDana S. Al-Saleh⁦2025-10-06⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planAbdulmajeed R. Al-Dosari⁦2025-10-01⁩
Final report — Final report and its approvalDana S. Al-Saleh⁦2025-10-26⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Later

Handover accepted — project owner

Abdulmajeed R. Al-Dosari

Later

Final financial settlement

Munirah A. Al-Khalidi

Later

Contracts closed, guarantees released

Mazen A. Al-Hazmi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

  2. Technical acceptance

    Handover accepted — project owner

    Abdulmajeed R. Al-Dosari · Project owner
  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

  4. Financial approval

    Contracts closed, guarantees released

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee
Waiting on Dana S. Al-Saleh

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Dana S. Al-Saleh

Only one version so far.