Budget (BAC)
Actual cost
94% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-08-28 | 2024-08-26 | −2 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-11-24 | 2024-11-21 | −3 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-04-06 | 2025-03-31 | −6 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-07-04 | 2025-06-26 | −8 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-09-30 | 2025-09-21 | −9 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline032-D1 | 4% | CRT-032-01 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Abdulmajeed R. Al-Dosari | 2024-07-15 | V1 | 3 of 3 |
| Monitoring & reporting032-D2 | 4% | CRT-032-02 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@chamber.sa | Abdulmajeed R. Al-Dosari | 2024-08-28 | V1 | 3 of 3 |
| Business requirements032-D3 | 9% | CRT-032-03 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@chamber.sa | Abdulmajeed R. Al-Dosari | 2024-10-11 | V1 | 3 of 3 |
| Solution design032-D4 | 9% | CRT-032-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Abdulmajeed R. Al-Dosari | 2024-11-24 | V1 | 3 of 3 |
| Release 1032-D5 | 13% | CRT-032-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-01-08 | V1 | 3 of 3 |
| Release 2032-D6 | 13% | CRT-032-06 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-02-21 | V1 | 3 of 3 |
| Integrations032-D7 | 13% | CRT-032-07 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-04-06 | V1 | 3 of 3 |
| System testing032-D8 | 10% | CRT-032-08 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-05-20 | V1 | 3 of 3 |
| User acceptance testing032-D9 | 10% | CRT-032-09 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-07-04 | V1 | 3 of 3 |
| Training & change032-D10 | 8% | CRT-032-10 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-08-17 | V1 | 3 of 3 |
| Go-live & handover032-D11 | 7% | CRT-032-11 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Abdulmajeed R. Al-Dosari | 2025-09-30 | V1 | 3 of 3 |
| Total · 11 | 100% |