RC/2024/008
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
68% of the current value paid
Paid
660Kof a current value of SAR 975K
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 20 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 20September 2026 | 2026-10-06 | 13.5K | 675 | 0 | 1,924 | 14.7K | Approved | |
| Certificate 19July 2026 | 2026-08-20 | 19K | 950 | 0 | 2,708 | 20.8K | Approved | |
| Certificate 18June 2026 | 2026-07-03 | 26.5K | 1,325 | 0 | 3,776 | 29K | Approved | |
| Certificate 17April 2026 | 2026-05-17 | 27K | 1,350 | 0 | 3,848 | 29.5K | Approved | |
| Certificate 16March 2026 | 2026-03-30 | 33.5K | 1,675 | 0 | 4,774 | 36.6K | Approved | |
| Certificate 15January 2026 | 2026-02-11 | 40K | 2,000 | 0 | 5,700 | 43.7K | Approved | |
| Certificate 14December 2025 | 2025-12-25 | 36K | 1,800 | 0 | 5,130 | 39.3K | Approved | |
| Certificate 13October 2025 | 2025-11-08 | 45.5K | 2,275 | 0 | 6,484 | 49.7K | Approved | |
| Certificate 12September 2025 | 2025-09-21 | 45K | 2,250 | 0 | 6,413 | 49.2K | Approved | |
| Certificate 11July 2025 | 2025-08-05 | 41K | 2,050 | 0 | 5,843 | 44.8K | Approved | |
| Certificate 10May 2025 | 2025-06-18 | 50K | 2,500 | 0 | 7,125 | 54.6K | Approved | |
| Certificate 9April 2025 | 2025-05-02 | 42K | 2,100 | 0 | 5,985 | 45.9K | Approved | |
| Certificate 8February 2025 | 2025-03-15 | 41K | 2,050 | 0 | 5,843 | 44.8K | Approved | |
| Certificate 7January 2025 | 2025-01-27 | 44K | 2,200 | 0 | 6,270 | 48.1K | Approved | |
| Certificate 6November 2024 | 2024-12-10 | 34K | 1,700 | 0 | 4,845 | 37.1K | Approved | |
| Certificate 5October 2024 | 2024-10-24 | 34K | 1,700 | 0 | 4,845 | 37.1K | Approved | |
| Certificate 4August 2024 | 2024-09-06 | 30.5K | 1,525 | 0 | 4,346 | 33.3K | Approved | |
| Certificate 3July 2024 | 2024-07-21 | 22.5K | 1,125 | 0 | 3,206 | 24.6K | Approved | |
| Certificate 2May 2024 | 2024-06-03 | 20.5K | 1,025 | 0 | 2,921 | 22.4K | Approved | |
| Certificate 1March 2024 | 2024-04-17 | 14.5K | 725 | 0 | 2,066 | 15.8K | Approved |