Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦25⁩ — June 2026

New chamber headquarters — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
25
Date
⁦2026-07-05⁩
Hijri
20 Muharram 1448 AH
Reference
PAY-2024-011-25

Interim payment certificate no. (⁦25⁩)

For the work of June 2026

Contract number
RC/2024/011
Supplier-portal reference
2401780147
Contract
New chamber headquarters — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s New Headquarters Building
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
51,000,000
Current contract value
52,925,000including variations of SAR 1.9M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date20,722,500
2Less: previous certificates(20,309,000)
3Value of work in this certificate413,500
4Less: retention (⁦10%⁩)(41,350)
5Less: advance payment recovery (⁦10%⁩)(41,350)
6Less: delay and breach penalties0
7Total deductions(82,700)
8Net before VAT330,800
9Add: value added tax (15%)49,620
10Net amount payable to the contractor380,420

Amount in words: Three hundred eighty thousand four hundred twenty Saudi riyals only

Retention held up to this certificate: SAR 2.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,704,7503,288,45058,2503,346,700⁦90%⁩
Earthworks & foundations9,526,5005,127,70094,3505,222,050⁦55%⁩
Concrete & structural works16,406,7506,924,400141,9507,066,350⁦43%⁩
Mechanical, electrical & plumbing12,702,0003,402,10079,3003,481,400⁦27%⁩
Finishes & external works7,938,7501,364,55034,2001,398,750⁦18%⁩
Testing & commissioning2,646,250201,8005,450207,250⁦8%⁩
Total52,925,00020,309,000413,50020,722,500⁦39%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-07-05⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-07⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-07-10⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-13⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-16⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-05⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-07-07⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-10⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2026-07-13⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-16⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

16 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-16 13:00

13 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-07-10 13:00

7 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-07 13:00

5 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close