RC/2024/011
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 210K — if approved the value becomes SAR 53.1M
41% of the current value paid
Paid
21.9Mof a current value of SAR 52.9M
Value of each certificate
The last 14 — gross and net
Approved: 27
Count: 28 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 28September 2026 | 2026-10-07 | 740K | 74K | 74K | 88.8K | 680.8K | In review | |
| Certificate 27August 2026 | 2026-09-07 | 845K | 84.5K | 84.5K | 101.4K | 777.4K | Approved | |
| Certificate 26July 2026 | 2026-08-06 | 342.5K | 34.3K | 34.3K | 41.1K | 315.1K | Approved | |
| Certificate 25June 2026 | 2026-07-05 | 413.5K | 41.4K | 41.4K | 49.6K | 380.4K | Approved | |
| Certificate 24May 2026 | 2026-06-02 | 549.5K | 55K | 55K | 65.9K | 505.5K | Approved | |
| Certificate 23April 2026 | 2026-05-01 | 641K | 64.1K | 64.1K | 76.9K | 589.7K | Approved | |
| Certificate 22March 2026 | 2026-03-29 | 653K | 65.3K | 65.3K | 78.4K | 600.8K | Approved | |
| Certificate 21February 2026 | 2026-02-25 | 862K | 86.2K | 86.2K | 103.4K | 793K | Approved | |
| Certificate 20January 2026 | 2026-01-23 | 843.5K | 84.4K | 84.4K | 101.2K | 776K | Approved | |
| Certificate 19December 2025 | 2025-12-22 | 882K | 88.2K | 88.2K | 105.8K | 811.4K | Approved | |
| Certificate 18October 2025 | 2025-11-19 | 1.1M | 109.4K | 109.4K | 131.2K | 1M | Approved | |
| Certificate 17September 2025 | 2025-10-18 | 948K | 94.8K | 94.8K | 113.8K | 872.2K | Approved | |
| Certificate 16August 2025 | 2025-09-15 | 1.1M | 107.8K | 107.8K | 129.3K | 991.3K | Approved | |
| Certificate 15July 2025 | 2025-08-14 | 1.2M | 118K | 118K | 141.6K | 1.1M | Approved | |
| Certificate 14June 2025 | 2025-07-12 | 984K | 98.4K | 98.4K | 118.1K | 905.3K | Approved | |
| Certificate 13May 2025 | 2025-06-10 | 1.2M | 118.4K | 118.4K | 142K | 1.1M | Approved | |
| Certificate 12April 2025 | 2025-05-08 | 1.1M | 111.5K | 111.5K | 133.8K | 1M | Approved | |
| Certificate 11March 2025 | 2025-04-06 | 971.5K | 97.2K | 97.2K | 116.6K | 893.8K | Approved | |
| Certificate 10February 2025 | 2025-03-04 | 1.1M | 114.4K | 114.4K | 137.3K | 1.1M | Approved | |
| Certificate 9January 2025 | 2025-01-31 | 944K | 94.4K | 94.4K | 113.3K | 868.5K | Approved | |
| Certificate 8December 2024 | 2024-12-29 | 896.5K | 89.7K | 89.7K | 107.6K | 824.8K | Approved | |
| Certificate 7November 2024 | 2024-11-27 | 950K | 95K | 95K | 114K | 874K | Approved | |
| Certificate 6October 2024 | 2024-10-25 | 727K | 72.7K | 72.7K | 87.2K | 668.8K | Approved | |
| Certificate 5September 2024 | 2024-09-23 | 726K | 72.6K | 72.6K | 87.1K | 667.9K | Approved | |
| Certificate 4August 2024 | 2024-08-21 | 653.5K | 65.4K | 65.4K | 78.4K | 601.2K | Approved | |
| Certificate 3June 2024 | 2024-07-20 | 495K | 49.5K | 49.5K | 59.4K | 455.4K | Approved | |
| Certificate 2May 2024 | 2024-06-17 | 452K | 45.2K | 45.2K | 54.2K | 415.8K | Approved | |
| Certificate 1April 2024 | 2024-05-16 | 337K | 33.7K | 33.7K | 40.4K | 310K | Approved |