Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 21
- Date
- 2026-02-25
- Hijri
- 8 Ramadan 1447 AH
- Reference
- PAY-2024-011-21
Interim payment certificate no. (21)
For the work of February 2026
- Contract number
- RC/2024/011
- Supplier-portal reference
- 2401780147
- Contract
- New chamber headquarters — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- The Chamber’s New Headquarters Building
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 51,000,000
- Current contract value
- 52,925,000including variations of SAR 1.9M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 18,465,500 |
| 2 | Less: previous certificates | (17,603,500) |
| 3 | Value of work in this certificate | 862,000 |
| 4 | Less: retention (10%) | (86,200) |
| 5 | Less: advance payment recovery (10%) | (86,200) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (172,400) |
| 8 | Net before VAT | 689,600 |
| 9 | Add: value added tax (15%) | 103,440 |
| 10 | Net amount payable to the contractor | 793,040 |
Amount in words: Seven hundred ninety-three thousand forty Saudi riyals only
Retention held up to this certificate: SAR 1.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,704,750 | 2,858,250 | 123,950 | 2,982,200 | 80% |
| Earthworks & foundations | 9,526,500 | 4,453,600 | 199,700 | 4,653,300 | 49% |
| Concrete & structural works | 16,406,750 | 6,001,100 | 295,650 | 6,296,750 | 38% |
| Mechanical, electrical & plumbing | 12,702,000 | 2,939,850 | 162,350 | 3,102,200 | 24% |
| Finishes & external works | 7,938,750 | 1,176,950 | 69,450 | 1,246,400 | 16% |
| Testing & commissioning | 2,646,250 | 173,750 | 10,900 | 184,650 | 7% |
| Total | 52,925,000 | 17,603,500 | 862,000 | 18,465,500 | 35% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani