Certificate ⁦28⁩ — September 2026

New chamber headquarters — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
28
Date
⁦2026-10-07⁩
Hijri
26 Rabiʻ II 1448 AH
Reference
PAY-2026-015

Interim payment certificate no. (⁦28⁩)

For the work of September 2026

Contract number
RC/2024/011
Supplier-portal reference
2401780147
Contract
New chamber headquarters — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s New Headquarters Building
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
51,000,000
Current contract value
52,925,000including variations of SAR 1.9M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date22,650,000
2Less: previous certificates(21,910,000)
3Value of work in this certificate740,000
4Less: retention (⁦10%⁩)(74,000)
5Less: advance payment recovery (⁦10%⁩)(74,000)
6Less: delay and breach penalties0
7Total deductions(148,000)
8Net before VAT592,000
9Add: value added tax (15%)88,800
10Net amount payable to the contractor680,800

Amount in words: Six hundred eighty thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 2.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,704,7503,555,800102,1503,657,950⁦99%⁩
Earthworks & foundations9,526,5005,541,250166,5505,707,800⁦60%⁩
Concrete & structural works16,406,7507,469,350254,3007,723,650⁦47%⁩
Mechanical, electrical & plumbing12,702,0003,660,950144,2503,805,200⁦30%⁩
Finishes & external works7,938,7501,466,15062,7501,528,900⁦19%⁩
Testing & commissioning2,646,250216,50010,000226,500⁦9%⁩
Total52,925,00021,910,000740,00022,650,000⁦43%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-10-07⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-10-12⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-10-19⁩

Finance & contracts

Khalid N. Al-Mutairi

Awaiting signature

Final approver

Dr. Abdullah S. Al-Qahtani

Later
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Current step: Payment order prepared

  1. Certificate submitted⁦2026-10-07⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-10-12⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 5 days

  3. Project manager certifies⁦2026-10-19⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 7 days

  4. Payment order preparedDue today2026-10-2817 Jumada I 1448 AH

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Waiting for Khalid N. Al-Mutairi
  5. Final approval

    Dr. Abdullah S. Al-Qahtani · Secretary-General

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

19 October 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-10-19 13:00

12 October 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-10-12 13:00

7 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-07 09:00