Certificate ⁦22⁩ — March 2026

New chamber headquarters — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
22
Date
⁦2026-03-29⁩
Hijri
10 Shawwal 1447 AH
Reference
PAY-2024-011-22

Interim payment certificate no. (⁦22⁩)

For the work of March 2026

Contract number
RC/2024/011
Supplier-portal reference
2401780147
Contract
New chamber headquarters — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s New Headquarters Building
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
51,000,000
Current contract value
52,925,000including variations of SAR 1.9M
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date19,118,500
2Less: previous certificates(18,465,500)
3Value of work in this certificate653,000
4Less: retention (⁦10%⁩)(65,300)
5Less: advance payment recovery (⁦10%⁩)(65,300)
6Less: delay and breach penalties0
7Total deductions(130,600)
8Net before VAT522,400
9Add: value added tax (15%)78,360
10Net amount payable to the contractor600,760

Amount in words: Six hundred thousand seven hundred sixty Saudi riyals only

Retention held up to this certificate: SAR 1.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,704,7502,994,30093,3503,087,650⁦83%⁩
Earthworks & foundations9,526,5004,667,200150,6504,817,850⁦51%⁩
Concrete & structural works16,406,7506,295,350224,0506,519,400⁦40%⁩
Mechanical, electrical & plumbing12,702,0003,088,250123,6503,211,900⁦25%⁩
Finishes & external works7,938,7501,237,50053,0001,290,500⁦16%⁩
Testing & commissioning2,646,250182,9008,300191,200⁦7%⁩
Total52,925,00018,465,500653,00019,118,500⁦36%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-03-29⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-03-31⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-04-03⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-04-06⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-04-09⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-29⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-03-31⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-03⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2026-04-06⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-04-09⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-01-13⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

9 April 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-04-09 13:00

6 April 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-04-06 13:00

3 April 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-04-03 13:00

31 March 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-03-31 13:00

29 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-29 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close