Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦3⁩ — June 2024

New chamber headquarters — construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2024-07-20⁩
Hijri
14 Muharram 1446 AH
Reference
PAY-2024-011-03

Interim payment certificate no. (⁦3⁩)

For the work of June 2024

Contract number
RC/2024/011
Supplier-portal reference
2401780147
Contract
New chamber headquarters — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s New Headquarters Building
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
51,000,000
Current contract value
52,925,000including variations of SAR 1.9M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date1,284,000
2Less: previous certificates(789,000)
3Value of work in this certificate495,000
4Less: retention (⁦10%⁩)(49,500)
5Less: advance payment recovery (⁦10%⁩)(49,500)
6Less: delay and breach penalties0
7Total deductions(99,000)
8Net before VAT396,000
9Add: value added tax (15%)59,400
10Net amount payable to the contractor455,400

Amount in words: Four hundred fifty-five thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 128.4K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation3,704,750127,90079,500207,400⁦6%⁩
Earthworks & foundations9,526,500199,350124,200323,550⁦3%⁩
Concrete & structural works16,406,750269,000168,850437,850⁦3%⁩
Mechanical, electrical & plumbing12,702,000132,00083,700215,700⁦2%⁩
Finishes & external works7,938,75052,90033,75086,650⁦1%⁩
Testing & commissioning2,646,2507,8505,00012,850⁦0%⁩
Total52,925,000789,000495,0001,284,000⁦2%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2024-07-20⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-07-22⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2024-07-25⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-07-28⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-07-31⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-07-20⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2024-07-22⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-07-25⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2024-07-28⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-07-31⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-02-27⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-05-07⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

31 July 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-07-31 13:00

28 July 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-07-28 13:00

25 July 2024

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2024-07-25 13:00

22 July 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-07-22 13:00

20 July 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-07-20 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close