The Chamber’s New Headquarters Building
Remove from watchlistA new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
SAR +4.4M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-11-09 | 2025-05-27 | +199 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-05-20 | 2026-05-07 | +352 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-05 | 2027-01-17 | +318 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-19 | 2027-06-19 | +182 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-06-30 | 2027-09-29 | +91 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
42%Awaiting acceptance
11%Not handed in
47%Deliverable flow
Display options
| Project plan & baseline002-D1 | 4% | CRT-002-01 | Approved | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-08-04 | V1 | 3 of 3 |
| Monitoring & reporting002-D2 | 4% | CRT-002-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-11-09 | V1 | 3 of 3 |
| Detailed design002-D3 | 8% | CRT-002-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-02-13 | V1 | 3 of 3 |
| Permits & approvals002-D4 | 8% | CRT-002-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-05-20 | V1 | 3 of 3 |
| Site works & excavation002-D5 | 18% | CRT-002-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-08-25 | V1 | 3 of 3 |
| Structure002-D6 | 11% | — | Under review | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-11-29 | V1 | 1 of 3 |
| Finishes002-D7 | 11% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-03-05 | V0 | 0 of 3 |
| Supply002-D8 | 8% | — | Draft | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-06-10 | V0 | 0 of 3 |
| Installation002-D9 | 8% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-09-14 | V0 | 0 of 3 |
| Testing & commissioning002-D10 | 8% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-12-19 | V0 | 0 of 3 |
| Provisional acceptance002-D11 | 6% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-03-26 | V0 | 0 of 3 |
| Final acceptance002-D12 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2027-06-30 | V0 | 0 of 3 |
| Total · 12 | 100% |