Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2024-12-05⁩
Hijri
4 Jumada II 1446 AH
ApprovedCRT-002-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
The Chamber’s New Headquarters Building
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ahmed Y. Asiri

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Ahmed Y. Asiri
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦4%⁩
DueAuto-filled
⁦2024-08-04⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-002_1.1_v1.pdfV1Eng. Ahmed Y. Asiri⁦2024-03-03⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2024-011
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsSubmitted—⁦2024-03-03⁩ 12:57
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-03-05⁩ 10:43
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2024-03-10⁩ 11:50
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-03-11⁩ 09:12
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-03-13⁩ 10:49

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2024-03-05⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2024-03-10⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2024-03-11⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2024-03-13⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2024-03-03⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-03-05⁩ at ⁦10:43⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-03-10⁩ at ⁦11:50⁩ · On behalf of Eng. Bandar M. Al-Shammari (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-03-11⁩ at ⁦09:12⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-03-13⁩ at ⁦10:49⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-03-03⁩

    PRJ-2026-002_1.1_v1.pdf

    Eng. Ahmed Y. Asiri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close