PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-03-28⁩
Hijri
18 Ramadan 1445 AH
ApprovedPRJ-2026-002The Chamber’s New Headquarters Building

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
The Chamber’s New Headquarters Building
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ahmed Y. Asiri

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-03-03⁩

Baseline finish

⁦2027-06-30⁩

Forecast finish

⁦2027-09-12⁩

SPI

0.82

MilestonePlannedForecastSlip
Project plan approved⁦2024-11-09⁩⁦2025-05-27⁩+199 days
Designs approved⁦2025-05-20⁩⁦2026-05-07⁩+352 days
Build complete⁦2026-03-05⁩⁦2027-01-17⁩+318 days
Testing & acceptance complete⁦2026-12-19⁩⁦2027-06-19⁩+182 days
Final handover⁦2027-06-30⁩⁦2027-09-29⁩+91 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦4%⁩⁦2024-08-04⁩Eng. Ahmed Y. Asiri
Monitoring & reporting⁦4%⁩⁦2024-11-09⁩Eng. Bandar M. Al-Shammari
Detailed design⁦8%⁩⁦2025-02-13⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦8%⁩⁦2025-05-20⁩Sarah A. Al-Qarni
Site works & excavation⁦18%⁩⁦2025-08-25⁩Sarah A. Al-Qarni
Structure⁦11%⁩⁦2025-11-29⁩Eng. Ahmed Y. Asiri
Finishes⁦11%⁩⁦2026-03-05⁩Eng. Bandar M. Al-Shammari
Supply⁦8%⁩⁦2026-06-10⁩Eng. Ahmed Y. Asiri
Installation⁦8%⁩⁦2026-09-14⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦8%⁩⁦2026-12-19⁩Sarah A. Al-Qarni
Provisional acceptance⁦6%⁩⁦2027-03-26⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦6%⁩⁦2027-06-30⁩Sarah A. Al-Qarni
Accepted with a certificate⁦42%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0015Steel and concrete price rises driving price-adjustment claims20EscalateEng. Ahmed Y. Asiri
RSK-0016Late handover of the northern plot and utility diversions in zones 3 and 420EscalateEng. Bandar M. Al-Shammari
RSK-0017Contractor claim for a 120-day extension with compensation16MitigateKhalid N. Al-Mutairi
RSK-0018Safety incidents around cranes and deep excavations10MitigateEng. Ahmed Y. Asiri

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Ahmed Y. Asiri
Project ownerDeliverable status and acceptance datesFortnightlyEng. Ahmed Y. Asiri
PMOData and indicator updatesWeeklyEng. Ahmed Y. Asiri
BeneficiariesWhat changes and whenAt each milestoneEng. Ahmed Y. Asiri
Team memberRoleAllocation
Eng. Ahmed Y. AsiriProject manager⁦60%⁩
Eng. Turki A. Al-AnaziBeneficiary lead — training halls in the new HQ⁦20%⁩
Haifa S. Al-RuwailiFinancial analyst⁦15%⁩
—Planning & scheduling engineer⁦50%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Ibrahim A. Al-Ghamdi
Review cadenceAuto-filled
Inspection before every pour across the six buildings; backfill tests in every zone
Next reviewAuto-filled
⁦2026-11-05⁩
Quality criterionThresholdNowMet
Backfill compaction under the slabs95% of max dry density or more92.8% in zone 3No
Floor screed thickness50 mm ±551 mm after repairYes
Fire rating of doors and separating walls120 minutes or more120 minutes in the tested samplesYes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsSubmitted—⁦2024-03-28⁩ 12:03
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2024-04-02⁩ 14:05
3Technical acceptance — project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2024-04-03⁩ 09:12
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-04-04⁩ 13:58
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-04-08⁩ 14:35
6Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2024-04-09⁩ 12:33

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2024-04-02⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Approved⁦2024-04-03⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2024-04-04⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2024-04-08⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2024-04-09⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2024-03-28⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-04-02⁩ at ⁦14:05⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-04-03⁩ at ⁦09:12⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-04-04⁩ at ⁦13:58⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-04-08⁩ at ⁦14:35⁩

  5. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2024-04-09⁩ at ⁦12:33⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-03-28⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Ahmed Y. Asiri

  2. V1Returned for edit⁦2024-03-14⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Ahmed Y. Asiri