Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 59M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 4.4M
EAC SAR 63.4M
Revised request SAR 59M
  • Actual spendSAR 26.6M
  • Committed, not spentSAR 28.2M
  • Allotted, uncommittedSAR 2.4M
  • Contingency availableSAR 1.8M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 52.5M
Original budgetwhen the first baseline was approved
SAR 57.1M
Approved budgetafter approved change requests
SAR 59M
Current budgetavailable to spend now
SAR 59M
Revised budgetif the pending changes are approved
SAR 59M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 54.8M
Contracts2 active contracts
SAR 54.3M
Purchase orders⁦3⁩ orders
SAR 555K
Remaining budgetapproved less actual
SAR 32.4M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 26.6M
Accrualswork done, not yet invoiced
SAR 1.1M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 63.4M
ContingencySAR 1.2M drawn of SAR 3M
SAR 1.8M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 52.5M
ApprovedSAR 59M
Estimate at completionSAR 63.4M
Approved is SAR 6.5M (⁦12.4%⁩) above the estimate
The estimate at completion is SAR 10.9M (⁦20.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2023-12-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-71002
  • WBS elements⁦5⁩ elements · P-2026-002.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦47⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 1.2M drawn of SAR 3M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 1.2M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance3.433.813.813.81⁦−0.38⁩
2Design & permits6.877.627.627.62⁦−0.76⁩
3Civil works21.7521.0215.2122.61⁦−0.86⁩
4MEP works17.1715.250.0019.44⁦−2.27⁩
5Handover8.017.120.009.07⁦−1.06⁩
Unallocated contingency1.770.000.000.89⁦+0.89⁩
Total59.0054.8226.6563.44⁦−4.44⁩

Budget split

WBS

SAR 59M

Budget

  • Management & governanceSAR 3.4M⁦6%⁩
  • Design & permitsSAR 6.9M⁦12%⁩
  • Civil worksSAR 21.7M⁦37%⁩
  • MEP worksSAR 17.2M⁦29%⁩
  • HandoverSAR 8M⁦14%⁩
  • Unallocated contingencySAR 1.8M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2030-02-15⁩+961

SPI(t) ⁦0.56⁩ against the approved finish ⁦2027-06-30⁩

Planned valuePV
SAR 52.9M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 24.8M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 26.6M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 59M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−1.87⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−28.08⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.93
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.47
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 63.4M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 36.8M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−4.44⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.06
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 63.4M
  • If the rest goes to planSAR 60.9M
  • At cost and schedule performanceSAR 105.1M
  • The PM’s bottom-up estimateSAR 63.4M
  • To stay within SAR 59M, cost performance on the rest must rise to ⁦1.06⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 63.4M

Variance at completion: ⁦−4.44⁩ SAR M