A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.
Early warning: 88% chance of slipping within 60 days
Budget (BAC)
SAR 59M
Actual cost
SAR 26.6M
45% of budget
Progress
42%Awaiting acceptance 11%
Estimate at completion
SAR 63.4M
SAR +4.4M
SPI · CPI
0.82Schedule performance index · 0.820.93Cost performance index · 0.93
Forecast finish
2027-09-12
74 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure25 March 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+91 days vs approved
Baseline (original = approved)2027-06-30
Current forecast2027-09-29
By earned schedule2030-02-15
Critical activities
7
of 10 open activities
Late activities
7
past their baseline finish
Schedule performance
0.47
earned ÷ planned value
Next milestone
in 81 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2024
2025
2026
2027
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Today
2027-09-2942%
The Chamber’s New Headquarters BuildingPlanned: 2024-03-03 → 2027-06-30Forecast: 2024-03-03 → 2027-09-29Float: 0d