1RC-PMO-F01Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
SAR +4.4M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
The project’s twelve forms with their status and approval path, each printable with its approval log.
Forms
16In approval
2Past their limit
1Escalated automatically
0Approved
141RC-PMO-F01Proposal
Justification, objectives, benefits, cost and initial risks
2RC-PMO-F02Proposal
Criteria, weights and the P1–P4 result
3RC-PMO-F03Approval
The weight and the relative weight in the portfolio
4RC-PMO-F04Initiation
Objective, scope, deliverables, roles and budget
5RC-PMO-F05Planning
Schedule, deliverables, risks, communications, quality and benefits
6RC-PMO-F06Planning
Roles, tasks, decisions and the start of execution
7RC-PMO-F07Execution
Progress, status, risks and support requested
8RC-PMO-F08Execution
Evidence, inspection, acceptance and the financial link
6 copies
9RC-PMO-F09Execution
The change, its impact analysis and the approval decision
10RC-PMO-F10Execution
The decision, the rationale and the approvals
Not yet · Opens at the «Execution» stage
11RC-PMO-F11Execution
Actions, owners, dates and status
Not yet · Opens at the «Execution» stage
12RC-PMO-F12Closure
Performance, handover, open commitments and lessons learned
Not yet · Opens at the «Closure» stage