PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-08-06⁩
Hijri
19 Muharram 1445 AH
ApprovedDMD-2026-002The Chamber’s New Headquarters Building

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
The Chamber’s New Headquarters Building
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ahmed Y. Asiri

1The proposalAuto-filled

TitleAuto-filled
The Chamber’s New Headquarters Building
Proposed byAuto-filled
Eng. Ahmed Y. Asiri
DepartmentAuto-filled
Construction Projects & Buildings Department
Submitted onAuto-filled
⁦2023-08-06⁩
Proposal numberAuto-filled
DMD-2026-002

2Justification

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

3Objectives

  1. The chamber’s services across Riyadh city and its governorates
  2. Active sectoral committees and business challenges resolved

Strategic objectives served

  • SO-2.3 — The chamber’s services across Riyadh city and its governorates
  • SO-1.2 — Active sectoral committees and business challenges resolved

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 59M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 42.5M
Supervision & consultingSAR 8.3M
Internal teamSAR 5.3M
Contingency reserve (5%)SAR 3M
TotalSAR 59M

6Initial risks

RiskLevelProposed response
Steel and concrete price rises driving price-adjustment claimsHighTreated in the risk management plan
Late handover of the northern plot and utility diversions in zones 3 and 4HighTreated in the risk management plan
Contractor claim for a 120-day extension with compensationHighTreated in the risk management plan
Safety incidents around cranes and deep excavationsMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsSubmitted—⁦2023-08-06⁩ 10:31
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-08-08⁩ 14:41
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-08-09⁩ 09:48
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-08-13⁩ 10:55
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-08-15⁩ 10:07
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-08-20⁩ 12:09

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-08-08⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-08-09⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2023-08-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-08-15⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-08-20⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2023-08-06⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-08-08⁩ at ⁦14:41⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-08-09⁩ at ⁦09:48⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2023-08-13⁩ at ⁦10:55⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-08-15⁩ at ⁦10:07⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-08-20⁩ at ⁦12:09⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-08-27⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Ahmed Y. Asiri

  2. V1Returned for edit⁦2023-08-06⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Ahmed Y. Asiri