PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

The Chamber’s New Headquarters Building

APPROVEDV2Approved ⁦2024-03-01⁩

1Project identity

Required at this stage
Project name
The Chamber’s New Headquarters Building
Project code
PRJ-2026-002
Project sponsor
Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa
Project manager
Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa
Portfolio & programme
New Headquarters & Investment Assets PortfolioNew Headquarters & Investment Assets Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

3Objectives

Required at this stage
  1. 1The chamber’s services across Riyadh city and its governorates
  2. 2Active sectoral committees and business challenges resolved

4Scope

Required at this stage

In scope

  • A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.
  • Saudi Building Code compliance
  • An approved plan to keep member services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep member services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-04-21⁩
2Main deliverable — stage 1⁦2025-11-12⁩
3Main deliverable — final stage⁦2027-01-11⁩
4Final report⁦2027-06-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-03-01⁩
  2. Contract signed⁦2024-09-13⁩
  3. 50% of works complete⁦2025-11-12⁩
  4. Provisional acceptance⁦2027-03-25⁩
  5. Closure⁦2027-06-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩42.5M
  • Supervision & consulting⁦14.0%⁩8.3M
  • Internal team⁦9.0%⁩5.3M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩3M
The owning sector’s approved budgetTotal59M

9Timeline

Required at this stage
Start
2024-03-0322 Shaʻban 1445 AH
Baseline finish
2027-06-3025 Muharram 1449 AH
Duration
⁦40⁩ months

10Key risks

Required at this stage
  • HighSteel and concrete price rises driving price-adjustment claims
  • High⁦Late handover of the northern plot and utility diversions in zones 3 and 4⁩
  • High⁦Contractor claim for a 120⁩-day extension with compensation
  • MediumSafety incidents around cranes and deep excavations

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the chamber
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close