Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Periodic update — September 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
RC-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-02⁩
Hijri
21 Rabiʻ II 1448 AH
ApprovedUPD-002-2026-09Periodic update — September 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
The Chamber’s New Headquarters Building
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ahmed Y. Asiri

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦40%⁩

+3 pts on the last period

Planned to date

⁦48%⁩

SPI

0.83

Actual cost

SAR 25M

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the August 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
Off track
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-09-12⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

Prefilled from the August 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0015Steel and concrete price rises driving price-adjustment claims20Eng. Ahmed Y. Asiri
RSK-0016Late handover of the northern plot and utility diversions in zones 3 and 420Eng. Bandar M. Al-Shammari
RSK-0017Contractor claim for a 120-day extension with compensation16Khalid N. Al-Mutairi
RSK-0018Safety incidents around cranes and deep excavations10Eng. Ahmed Y. Asiri
CodeImpedimentSeverity
ISS-0116Excavation clashing with a high-voltage line in zone 4High
ISS-0117Neighbour complaints about traffic diversions around the siteMedium
ISS-0118Conference and general-assembly hall designs awaiting approvalMedium

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SAR 49K), and the Secretary-General to press the NIC on the Nafath environment.

Prefilled from the August 2026 card — edit it if it changed

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsSubmitted—⁦2026-10-02⁩ 11:38
2PMO checkMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-10-04⁩ 13:58
3Sponsor review & approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2026-10-06⁩ 14:05

Signatures

PMO check

Ghada A. Al-Shahrani

Approved⁦2026-10-04⁩

Sponsor review & approval

Sarah A. Al-Qarni

Approved⁦2026-10-06⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2026-10-02⁩

  1. Methodology review

    PMO check

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-04⁩ at ⁦13:58⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2026-10-06⁩ at ⁦14:05⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-10-02⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Eng. Ahmed Y. Asiri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close