Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-002Off track4ExecutionConstructionStalled

The Chamber’s New Headquarters Building

Remove from watchlist

A new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 59M

Actual cost

SAR 26.6M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 63.4M

SAR +4.4M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

The Chamber’s New Headquarters Building

PRJ-2026-002 · Support Services Sector · Strategic · WP-2024-002

StalledOff track4ExecutionProject manager: Eng. Ahmed Y. Asiri · Sponsor: Sarah A. Al-Qarni
Progress
⁦42%⁩ / ⁦51%⁩
SPI · CPI
0.82 · 0.93
Spend
SAR 26.6M / SAR 59M
Estimate at completion
SAR 63.4M

Schedule

⁦9%⁩ behind⁦42%⁩

Planned to date ⁦51%⁩

Forecast finish: 2027-09-1211 Rabiʻ II 1449 AH · 74 days late

SPI0.82Schedule performance index · 0.82CPI0.93Cost performance index · 0.93

Health dimensions

Off track

Last update: 2026-10-2615 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2027-01-179 Shaʻban 1448 AH
  • Testing & acceptance complete2027-06-1914 Muharram 1449 AH
  • Final handover2027-09-2928 Rabiʻ II 1449 AH

Top risks

  • Steel and concrete price rises driving price-adjustment claims20
  • Late handover of the northern plot and utility diversions in zones 3 and 420
  • Contractor claim for a 120-day extension with compensation16
  • Safety incidents around cranes and deep excavations10

Open impediments

  • Excavation clashing with a high-voltage line in zone 4 · Escalated
  • Neighbour complaints about traffic diversions around the site · In progress
  • Conference and general-assembly hall designs awaiting approval · Open

Decisions and changes waiting

  • Review certificate 28 — new headquarters

Copilot summary

The scope holds 1 project with a budget of SAR 59M: 0 on track and 1 red or critical. Weighted progress is 42% against 51% planned, spend SAR 26.6M, and EAC SAR 63.4M (SAR 4.4M over).

1 project is more than a month behind baseline; the worst: The Chamber’s New Headquarters Building (74 days).

Riyadh Chamber of Commerce & Industry · prepared by Eng. Ahmed Y. Asiri in MunjazInternal

Status: Off track ·Project page