The Chamber’s New Headquarters Building
Remove from watchlistA new headquarters in north Riyadh housing the secretariat, the members’ service hall, the conference and general-assembly hall and the sectoral committee rooms in four linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
SAR +4.4M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth