Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 4
- Date
- 2024-08-21
- Hijri
- 17 Safar 1446 AH
- Reference
- PAY-2024-011-04
Interim payment certificate no. (4)
For the work of August 2024
- Contract number
- RC/2024/011
- Supplier-portal reference
- 2401780147
- Contract
- New chamber headquarters — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- The Chamber’s New Headquarters Building
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 51,000,000
- Current contract value
- 52,925,000including variations of SAR 1.9M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,937,500 |
| 2 | Less: previous certificates | (1,284,000) |
| 3 | Value of work in this certificate | 653,500 |
| 4 | Less: retention (10%) | (65,350) |
| 5 | Less: advance payment recovery (10%) | (65,350) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (130,700) |
| 8 | Net before VAT | 522,800 |
| 9 | Add: value added tax (15%) | 78,420 |
| 10 | Net amount payable to the contractor | 601,220 |
Amount in words: Six hundred one thousand two hundred twenty Saudi riyals only
Retention held up to this certificate: SAR 193.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,704,750 | 208,250 | 104,600 | 312,850 | 8% |
| Earthworks & foundations | 9,526,500 | 324,650 | 163,600 | 488,250 | 5% |
| Concrete & structural works | 16,406,750 | 437,750 | 222,950 | 660,700 | 4% |
| Mechanical, electrical & plumbing | 12,702,000 | 214,650 | 110,850 | 325,500 | 3% |
| Finishes & external works | 7,938,750 | 86,000 | 44,800 | 130,800 | 2% |
| Testing & commissioning | 2,646,250 | 12,700 | 6,700 | 19,400 | 1% |
| Total | 52,925,000 | 1,284,000 | 653,500 | 1,937,500 | 4% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani