Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 7
- Date
- 2024-11-27
- Hijri
- 25 Jumada I 1446 AH
- Reference
- PAY-2024-011-07
Interim payment certificate no. (7)
For the work of November 2024
- Contract number
- RC/2024/011
- Supplier-portal reference
- 2401780147
- Contract
- New chamber headquarters — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- The Chamber’s New Headquarters Building
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 51,000,000
- Current contract value
- 52,925,000including variations of SAR 1.9M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 4,340,500 |
| 2 | Less: previous certificates | (3,390,500) |
| 3 | Value of work in this certificate | 950,000 |
| 4 | Less: retention (10%) | (95,000) |
| 5 | Less: advance payment recovery (10%) | (95,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (190,000) |
| 8 | Net before VAT | 760,000 |
| 9 | Add: value added tax (15%) | 114,000 |
| 10 | Net amount payable to the contractor | 874,000 |
Amount in words: Eight hundred seventy-four thousand Saudi riyals only
Retention held up to this certificate: SAR 434.1K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 3,704,750 | 550,750 | 150,250 | 701,000 | 19% |
| Earthworks & foundations | 9,526,500 | 858,050 | 235,750 | 1,093,800 | 11% |
| Concrete & structural works | 16,406,750 | 1,155,800 | 324,300 | 1,480,100 | 9% |
| Mechanical, electrical & plumbing | 12,702,000 | 565,950 | 163,250 | 729,200 | 6% |
| Finishes & external works | 7,938,750 | 226,550 | 66,450 | 293,000 | 4% |
| Testing & commissioning | 2,646,250 | 33,400 | 10,000 | 43,400 | 2% |
| Total | 52,925,000 | 3,390,500 | 950,000 | 4,340,500 | 8% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani