Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦7⁩ — May 2025

Chamber investment building — business tower construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
7
Date
⁦2025-05-23⁩
Hijri
25 Dhuʻl-Qiʻdah 1446 AH
Reference
PAY-2024-017-07

Interim payment certificate no. (⁦7⁩)

For the work of May 2025

Contract number
RC/2024/017
Supplier-portal reference
2402200225
Contract
Chamber investment building — business tower construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s Investment Building — Business Tower on King Fahd Road
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
14,900,000
Current contract value
14,900,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date2,334,500
2Less: previous certificates(1,822,500)
3Value of work in this certificate512,000
4Less: retention (⁦10%⁩)(51,200)
5Less: advance payment recovery (⁦10%⁩)(51,200)
6Less: delay and breach penalties0
7Total deductions(102,400)
8Net before VAT409,600
9Add: value added tax (15%)61,440
10Net amount payable to the contractor471,040

Amount in words: Four hundred seventy-one thousand forty Saudi riyals only

Retention held up to this certificate: SAR 233.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,043,000297,75079,250377,000⁦36%⁩
Earthworks & foundations2,682,000463,250125,050588,300⁦22%⁩
Concrete & structural works4,619,000621,050175,000796,050⁦17%⁩
Mechanical, electrical & plumbing3,576,000302,20090,000392,200⁦11%⁩
Finishes & external works2,235,000120,50037,100157,600⁦7%⁩
Testing & commissioning745,00017,7505,60023,350⁦3%⁩
Total14,900,0001,822,500512,0002,334,500⁦16%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-05-23⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-05-25⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-05-28⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-05-31⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-06-03⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-05-23⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-05-25⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-05-28⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2025-05-31⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-06-03⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

3 June 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-06-03 13:00

31 May 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-05-31 13:00

28 May 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-05-28 13:00

25 May 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-05-25 13:00

23 May 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-05-23 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close