RC/2024/017
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 420K — if approved the value becomes SAR 15.3M
43% of the current value paid
Paid
6.4Mof a current value of SAR 14.9M
Value of each certificate
The last 14 — gross and net
Approved: 18
Count: 18 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 18September 2026 | 2026-10-05 | 325K | 32.5K | 32.5K | 39K | 299K | Approved | |
| Certificate 17August 2026 | 2026-09-03 | 156K | 15.6K | 15.6K | 18.7K | 143.5K | Approved | |
| Certificate 16June 2026 | 2026-07-18 | 226.5K | 22.7K | 22.7K | 27.2K | 208.4K | Approved | |
| Certificate 15May 2026 | 2026-06-01 | 305K | 30.5K | 30.5K | 36.6K | 280.6K | Approved | |
| Certificate 14March 2026 | 2026-04-16 | 312.5K | 31.3K | 31.3K | 37.5K | 287.5K | Approved | |
| Certificate 13February 2026 | 2026-02-28 | 419.5K | 42K | 42K | 50.3K | 385.9K | Approved | |
| Certificate 12December 2025 | 2026-01-12 | 442.5K | 44.3K | 44.3K | 53.1K | 407.1K | Approved | |
| Certificate 11November 2025 | 2025-11-26 | 421.5K | 42.2K | 42.2K | 50.6K | 387.8K | Approved | |
| Certificate 10September 2025 | 2025-10-10 | 534K | 53.4K | 53.4K | 64.1K | 491.3K | Approved | |
| Certificate 9August 2025 | 2025-08-25 | 465.5K | 46.6K | 46.6K | 55.9K | 428.3K | Approved | |
| Certificate 8June 2025 | 2025-07-09 | 462.5K | 46.3K | 46.3K | 55.5K | 425.5K | Approved | |
| Certificate 7May 2025 | 2025-05-23 | 512K | 51.2K | 51.2K | 61.4K | 471K | Approved | |
| Certificate 6March 2025 | 2025-04-06 | 394K | 39.4K | 39.4K | 47.3K | 362.5K | Approved | |
| Certificate 5January 2025 | 2025-02-18 | 403.5K | 40.4K | 40.4K | 48.4K | 371.2K | Approved | |
| Certificate 4December 2024 | 2025-01-02 | 364K | 36.4K | 36.4K | 43.7K | 334.9K | Approved | |
| Certificate 3October 2024 | 2024-11-17 | 264K | 26.4K | 26.4K | 31.7K | 242.9K | Approved | |
| Certificate 2September 2024 | 2024-10-01 | 237K | 23.7K | 23.7K | 28.4K | 218K | Approved | |
| Certificate 1July 2024 | 2024-08-15 | 160K | 16K | 16K | 19.2K | 147.2K | Approved |