Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦16⁩ — June 2026

Chamber investment building — business tower construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
16
Date
⁦2026-07-18⁩
Hijri
4 Safar 1448 AH
Reference
PAY-2024-017-16

Interim payment certificate no. (⁦16⁩)

For the work of June 2026

Contract number
RC/2024/017
Supplier-portal reference
2402200225
Contract
Chamber investment building — business tower construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s Investment Building — Business Tower on King Fahd Road
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
14,900,000
Current contract value
14,900,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date5,924,000
2Less: previous certificates(5,697,500)
3Value of work in this certificate226,500
4Less: retention (⁦10%⁩)(22,650)
5Less: advance payment recovery (⁦10%⁩)(22,650)
6Less: delay and breach penalties0
7Total deductions(45,300)
8Net before VAT181,200
9Add: value added tax (15%)27,180
10Net amount payable to the contractor208,380

Amount in words: Two hundred eight thousand three hundred eighty Saudi riyals only

Retention held up to this certificate: SAR 592.4K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,043,000924,90031,800956,700⁦92%⁩
Earthworks & foundations2,682,0001,441,25051,6001,492,850⁦56%⁩
Concrete & structural works4,619,0001,942,35077,7502,020,100⁦44%⁩
Mechanical, electrical & plumbing3,576,000951,70043,550995,250⁦28%⁩
Finishes & external works2,235,000381,05018,800399,850⁦18%⁩
Testing & commissioning745,00056,2503,00059,250⁦8%⁩
Total14,900,0005,697,500226,5005,924,000⁦40%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-07-18⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-20⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-07-23⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-26⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-29⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-18⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-07-20⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-07-23⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2026-07-26⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-29⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-02-06⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

29 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-29 13:00

26 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-26 13:00

23 July 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-07-23 13:00

20 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-20 13:00

18 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close