Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 15
- Date
- 2026-06-01
- Hijri
- 15 Dhuʻl-Hijjah 1447 AH
- Reference
- PAY-2024-017-15
Interim payment certificate no. (15)
For the work of May 2026
- Contract number
- RC/2024/017
- Supplier-portal reference
- 2402200225
- Contract
- Chamber investment building — business tower construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- The Chamber’s Investment Building — Business Tower on King Fahd Road
- Contract period
- 2024-07-01 — 2027-05-31
- Original contract value
- 14,900,000
- Current contract value
- 14,900,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 5,697,500 |
| 2 | Less: previous certificates | (5,392,500) |
| 3 | Value of work in this certificate | 305,000 |
| 4 | Less: retention (10%) | (30,500) |
| 5 | Less: advance payment recovery (10%) | (30,500) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (61,000) |
| 8 | Net before VAT | 244,000 |
| 9 | Add: value added tax (15%) | 36,600 |
| 10 | Net amount payable to the contractor | 280,600 |
Amount in words: Two hundred eighty thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 569.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,043,000 | 876,950 | 43,150 | 920,100 | 88% |
| Earthworks & foundations | 2,682,000 | 1,365,900 | 69,850 | 1,435,750 | 54% |
| Concrete & structural works | 4,619,000 | 1,838,150 | 104,700 | 1,942,850 | 42% |
| Mechanical, electrical & plumbing | 3,576,000 | 898,950 | 58,250 | 957,200 | 27% |
| Finishes & external works | 2,235,000 | 359,500 | 25,100 | 384,600 | 17% |
| Testing & commissioning | 745,000 | 53,050 | 3,950 | 57,000 | 8% |
| Total | 14,900,000 | 5,392,500 | 305,000 | 5,697,500 | 38% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani