Riyadh ChamberMunjaz11My actionsNotifications

Certificate ⁦3⁩ — October 2024

Chamber investment building — business tower construction

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
3
Date
⁦2024-11-17⁩
Hijri
15 Jumada I 1446 AH
Reference
PAY-2024-017-03

Interim payment certificate no. (⁦3⁩)

For the work of October 2024

Contract number
RC/2024/017
Supplier-portal reference
2402200225
Contract
Chamber investment building — business tower construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
The Chamber’s Investment Building — Business Tower on King Fahd Road
Contract period
⁦2024-07-01⁩ — ⁦2027-05-31⁩
Original contract value
14,900,000
Current contract value
14,900,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SAR)

1Total value of work completed to date661,000
2Less: previous certificates(397,000)
3Value of work in this certificate264,000
4Less: retention (⁦10%⁩)(26,400)
5Less: advance payment recovery (⁦10%⁩)(26,400)
6Less: delay and breach penalties0
7Total deductions(52,800)
8Net before VAT211,200
9Add: value added tax (15%)31,680
10Net amount payable to the contractor242,880

Amount in words: Two hundred forty-two thousand eight hundred eighty Saudi riyals only

Retention held up to this certificate: SAR 66.1K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,043,00064,60042,200106,800⁦10%⁩
Earthworks & foundations2,682,000100,55066,000166,550⁦6%⁩
Concrete & structural works4,619,000135,30090,100225,400⁦5%⁩
Mechanical, electrical & plumbing3,576,00066,15044,900111,050⁦3%⁩
Finishes & external works2,235,00026,45018,15044,600⁦2%⁩
Testing & commissioning745,0003,9502,6506,600⁦1%⁩
Total14,900,000397,000264,000661,000⁦4%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2024-11-17⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-11-19⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2024-11-22⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-11-25⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-11-28⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-11-17⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2024-11-19⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-11-22⁩

    Eng. Ahmed Y. Asiri · Director, Construction Projects & Buildings

    Took 3 days

  4. Payment order prepared⁦2024-11-25⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-11-28⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-04-25⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-02-03⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

28 November 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-11-28 13:00

25 November 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-11-25 13:00

22 November 2024

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2024-11-22 13:00

19 November 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-11-19 13:00

17 November 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-11-17 09:00