Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 9
- Date
- 2026-09-04
- Hijri
- 22 Rabiʻ I 1448 AH
- Reference
- PAY-2025-005-09
Interim payment certificate no. (9)
For the work of August 2026
- Contract number
- RC/2025/005
- Supplier-portal reference
- 2503460459
- Contract
- Solar PV supply & installation — chamber buildings & branches
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for the Chamber’s Buildings & Branches
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 4,050,000
- Current contract value
- 4,050,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 2,005,000 |
| 2 | Less: previous certificates | (1,890,500) |
| 3 | Value of work in this certificate | 114,500 |
| 4 | Less: retention (10%) | (11,450) |
| 5 | Less: advance payment recovery (10%) | (11,450) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (22,900) |
| 8 | Net before VAT | 91,600 |
| 9 | Add: value added tax (15%) | 13,740 |
| 10 | Net amount payable to the contractor | 105,340 |
Amount in words: One hundred five thousand three hundred forty Saudi riyals only
Retention held up to this certificate: SAR 200.5K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 283,500 | 270,250 | 13,250 | 283,500 | 100% |
| Earthworks & foundations | 729,000 | 518,550 | 27,000 | 545,550 | 75% |
| Concrete & structural works | 1,255,500 | 644,300 | 39,400 | 683,700 | 54% |
| Mechanical, electrical & plumbing | 972,000 | 313,800 | 23,050 | 336,850 | 35% |
| Finishes & external works | 607,500 | 125,200 | 10,150 | 135,350 | 22% |
| Testing & commissioning | 202,500 | 18,400 | 1,650 | 20,050 | 10% |
| Total | 4,050,000 | 1,890,500 | 114,500 | 2,005,000 | 50% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani