Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 5
- Date
- 2026-01-12
- Hijri
- 23 Rajab 1447 AH
- Reference
- PAY-2025-005-05
Interim payment certificate no. (5)
For the work of December 2025
- Contract number
- RC/2025/005
- Supplier-portal reference
- 2503460459
- Contract
- Solar PV supply & installation — chamber buildings & branches
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for the Chamber’s Buildings & Branches
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 4,050,000
- Current contract value
- 4,050,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SAR)
| 1 | Total value of work completed to date | 1,167,500 |
| 2 | Less: previous certificates | (856,000) |
| 3 | Value of work in this certificate | 311,500 |
| 4 | Less: retention (10%) | (31,150) |
| 5 | Less: advance payment recovery (10%) | (31,150) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (62,300) |
| 8 | Net before VAT | 249,200 |
| 9 | Add: value added tax (15%) | 37,380 |
| 10 | Net amount payable to the contractor | 286,580 |
Amount in words: Two hundred eighty-six thousand five hundred eighty Saudi riyals only
Retention held up to this certificate: SAR 116.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 283,500 | 142,550 | 46,000 | 188,550 | 67% |
| Earthworks & foundations | 729,000 | 220,650 | 73,550 | 294,200 | 40% |
| Concrete & structural works | 1,255,500 | 291,400 | 106,700 | 398,100 | 32% |
| Mechanical, electrical & plumbing | 972,000 | 138,850 | 57,300 | 196,150 | 20% |
| Finishes & external works | 607,500 | 54,600 | 24,200 | 78,800 | 13% |
| Testing & commissioning | 202,500 | 7,950 | 3,750 | 11,700 | 6% |
| Total | 4,050,000 | 856,000 | 311,500 | 1,167,500 | 29% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani